| 1. |
Order Receiving: After orders received and confirmed by the Sales Department, they are sent to the Factory Administration Department to purchase the raw materials. |
| |
| 2. |
Wooden Pattern Checking & Work Distribution: Inspection of the pattern, work distribution and estimated finishing |
| |
dates are organized and double confirmed by the Production & Quality Control staff. |
| 3. |
Mold Making: The Casting Division executes production according to the mold-making requests and work distribution records provided by the Production & Quality Control division. |
| |
| 4. |
Melting: To record the CE value from the Carbon Equivalent Meter, and to adjust the percentage of composite raw |
| |
materials. |
| 5. |
Quality Control by Spectrometer Analysis: Quality control by executing chemical analysis, visual inspection of the cast iron parts and physical property testing of the samples. |
| |
| 6. |
Pouring |
| 7. |
Shakeout: Preparation for abrasive cleaning. |
| 8. |
Sand Blasting: This procedure involves abrasive blast cleaning, grinding, and providing centrally managed area for |
| |
removed risers. |
| 9. |
Heat Treatment: Temperature management and adjustment according to the thickness of cast iron parts. |
| 10. |
Inspection: Non-destructive testing including: Ultra-sonic testing; Still load compression resistance testing; Hardness |
| |
testing; Measurements reconfirmation…etc. |
| 11. |
Delivery: Customized branding and painting requests; Delivery to requested destinations. |